Jakarta-Cikampek elevated toll road construction to be halted during Idul Fitri

Selasa, 05 Juni 2018 / 16:55 WIB

Jakarta-Cikampek elevated toll road construction to be halted during Idul Fitri
ILUSTRASI. PEMBANGUNAN TOL JAKARTA-CIKAMPEK II

KONTAN.CO.ID - JAKARTA. State-owned toll road operator PT Jasa Marga has decided to temporarily halt the Jakarta-Cikampek elevated toll road construction in the city for 20 days during the Idul Fitri holiday.

“There’ll be no construction activity from 10 days before until 10 days after the Idul Fitri celebration,” said Jasa Marga president director Desi Arryani as quoted by kompas.com on Tuesday.


The Islamic holiday is expected to fall on June 15 and 16.

Jasa Marga spokesperson Dwimawan Heru said the company had already been halting construction projects for several days during public holidays to ensure the safety of the workers and people.

“But it won’t disrupt our schedule. The toll road construction will finish according to our target,” he said.

The elevated toll road is deemed a solution to ease traffic congestion that frequently occurs at the existing Jakarta-Cikampek toll road. The toll road, which stretches 36.4 kilometers, is expected to be finished in 2019.

Sumber : The Jakarta Post
Editor: Wahyu Rahmawati

Video Pilihan

TERBARU
Seleksi CPNS 2018
Hubungi Kami
Redaksi : Gedung KONTAN,
Jalan Kebayoran Lama No. 1119 Jakarta 12210.
021 5357636/5328134
moderator[at]kontan.co.id
Epaper[at]kontan.co.id
Iklan : Gedung KOMPAS GRAMEDIA Unit 2
Lt 2 Jl. Palmerah selatan 22-28
Jakarta Selatan 10740.
021 53679909/5483008 ext 7304,7306
2018 © Kontan.co.id All rights reserved
Sitemap | Profile | Term of Use | Pedoman Pemberitaan Media Siber | Privacy Policy

diagnostic_api_kiri = 0.0111 || diagnostic_api_kanan = 0.0751 || diagnostic_web = 0.5355

Close [X]
×